You are the project manager for your organization.

You are the project manager for your organization. You are discussing an upcoming project with management and they would like you to begin decomposing the project work packages into activities as soon as possible. You have explained to the management that you would like to involve your roject team before the decomposition of the work packages begins. Why would you want your project team to involve in this activity?

A.

To understand the exact type of work the project team will be completing

B.

To help the activity go faster

C.

To get better and more accurate results through the decomposition

D.

To create assignments for the project team as the activities are discussed

PMI-SP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-SP pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"