You are the project manager for your company.

You are the project manager for your company. You are working with the activities defined in the figure below.

What will happen to your project if Activity F takes five additional days to complete than what was expected?

A.

Your project's critical path will shift to ACFI.

B.

Your project will be late by five days.

C.

Your project can still complete on time as float is available on Activity I.

D.

Your project will now have two critical paths.