You are the project manager for your organization.

You are the project manager for your organization. You are coaching Allen, a junior project manager, on how the details of the project's critical path are calculated. Examine the figure given below:

What is the critical path of this project?

A.

ABEHJ

B.

ACFGJ

C.

ADGJ

D.

ACFIJ