Tom is the project manager of the GHQ Project for his organization.

Tom is the project manager of the GHQ Project for his organization. He is working on recovering the project schedule. As Tom examines his schedule he is especially aware of project activities with soft logic. What is soft logic?

A.

Soft logic describes activities that do not have particular resources assigned to them.

B.

Soft logic describes activities that can be completed in any order.

C.

Soft logic describes activities that can have lead time added to them.

D.

Soft logic describes activities that can be crashed because they are effort-driven.