Holly is a new project manager in your organization.

Holly is a new project manager in your organization. She is working with you on the JHG project and she is confused as to why the project needs a schedule management plan and a schedule baseline. What is the difference between the schedule management plan and the schedule baseline?

A.

The schedule management plan describes how the schedule will be managed and controlled. The schedule baseline is used to compare with actual results to determine if a change, corrective action, or preventive action is needed.

B.

The schedule management plan describes how the schedule will be managed and controlled. The schedule baseline is used to determine how accurate the schedule management plan has been throughout the project execution.

C.

The schedule baseline describes how the schedule will be managed and controlled. The schedule management plan is used to compare with actual results to determine if a change, corrective action, or preventive action is needed.

D.

The schedule management plan describes how the schedule will be created. The schedule baseline is used to compare with actual results with what the project manager intended.

PMI-SP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-SP pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"