PMI PMI-SP Question Answer
Gary is the project manager for his organization. At each weekly status meeting with his project team, Gary collects information on the work that has been completed and reviews the work that is remaining in the project. Alice, one of Gary's project team members, consistently reports that she's late on her project work. After the meeting, Gary and Alice discuss why the work is late as it is causing other delays in the project. What is the review of the late work commonly called?