Amy works as a project manager for BlueWell Inc.

Amy works as a project manager for BlueWell Inc. She is working on the SDI project, which has a BAC of $2,816,000. She is currently 20 percent complete with this project, though she should be 25 percent complete with the project work. The project has consumed $495,000 of the project budget to date. Management has asked her the project's Estimate To Complete (ETC) based on the current project performance. What is the ETC for this project?

A.

$1,312,504

B.

$1,979,952

C.

$1,541,544

D.

$2,474,952