The project manager and the risk manager of a new project to develop an application...

The project manager and the risk manager of a new project to develop an application to support autonomous driving are meeting with the sponsor and key stakeholders to discuss the project. During the meeting, it is identified that the transport authority is discussing new traffic regulations for the industry that could be in place before the project ends.

How should the project manager and the risk manager handle this situation?

A.

Ensure the project complies with the current traffic regulations and laws.

B.

Send a letter to the traffic authority with the general project information.

C.

Perform inquiries on the website of the traffic authority weekly.

D.

Meet with the traffic authority staff in charge of the new regulation.

PMI-RMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-RMP pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"