Stakeholder holiday schedules and availability of raw materials were two risks initially identified in a...

Stakeholder holiday schedules and availability of raw materials were two risks initially identified in a manufacturing project. The risk manager now notices that both risks are not quite as originally described and might require a plan change.

What should the risk manager do next?

A.

Consult with the project manager to agree that these risks should be removed from the risk register

B.

Keep the risks in the risk register and continue to follow up until the change actually takes place.

C.

Identify workarounds that can be implemented whether or not the change takes place.

D.

Revisit the project the assumptions and constraints to potentially update the risk impact and response. 

PMI-RMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-RMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"
Next
.