At the beginning of a small project, the risk manager facilitates workshops to identify and...

At the beginning of a small project, the risk manager facilitates workshops to identify and analyze risks. At the end of the sessions, a stakeholder says that there should be no need to meet again about the risk register now that it ' s complete since it is such a short and simple project.

How should the risk manager respond to this comment?

A.

The risk register must only be updated if a change is approved during the project.

B.

Agree on the condition that the risk register be updated if the project environment changes.

C.

Compromise by updating the risk register at the end of each phase only.

D.

Insist on continuous review and updating of the risk register during the project.

PMI-RMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-RMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"