As part of standard procedure to monitor and control a project, a risk manager should...

As part of standard procedure to monitor and control a project, a risk manager should constantly update the risk register. The risk register updates should include information on risk reassessment, risk audits, and periodic risk reviews.

What additional information should the risk manager prioritize in the risk register updates?

A.

Actual outcomes and performance of risk management strategies

B.

Actual outcomes of the project ' s risks and risk responses

C.

Actual costs and schedule delays of risk events

D.

Actual cost impact of risk events