A risk manager is reviewing documentation for a project following a risk planning workshop with...

A risk manager is reviewing documentation for a project following a risk planning workshop with project stakeholders and team members. Several items have been identified on the risk log that would be detrimental to project success, but the associated triggers cannot be managed by the organization and are unlikely to occur.

Which response should the risk manager recommend for these risk items?

A.

Mitigate

B.

Accept

C.

Enhance

D.

Exploit