A project manager has determined that they cannot outsource work nor eliminate the scope.

A project manager has determined that they cannot outsource work nor eliminate the scope. They also discover that they cannot buy insurance or mitigate the risk.

What should the project manager do?

A.

Avoid the risk

B.

Transfer the risk

C.

Ignore the risk

D.

Accept the risk