A certain risk is identified for a major project, and the risk response is planned.

A certain risk is identified for a major project, and the risk response is planned. However, the analysis reveals a high probability for a secondary risk which will be tolerated based on the organization's risk thresholds. The secondary risk is subsequently registered. During project execution, the primary risk occurs, the planned action is taken, and the secondary risk emerges

What two actions should the risk owner take? (Choose two.)

A.

Implement the secondary risk response and update the project documents.

B.

Conduct meeting with all stakeholder to agree on post impact solutions.

C.

Set the corresponding trigger conditions to the secondary risk.

D.

Engage the project manager to authorize the secondary risk's response.

E.

Update and communicate assessments of the secondary risk's impact.

PMI-RMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-RMP pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"