The PMO at a large company operating in a highly regulated industry is responsible for...

The PMO at a large company operating in a highly regulated industry is responsible for defining the project management processes for the company.

Which action should the PMO Professional take to ensure that the processes are adhered to?

A.

Execute regular audits to evaluate adherence to the processes.

B.

Schedule random meetings to follow up the process deliverables.

C.

Trust the project teams to follow the processes and comply with the systems.

D.

Occasionally follow up the process deliverables of the most important projects.