When a change request is received, the business analyst is responsible for:
A.
analyzing the impact to the project schedule and budget.
B.
ensuring that change-related incidents are minimized in production.
C.
analyzing the impact on business and underlying systems.
D.
prioritizing and scheduling the changes requested.
The Answer Is:
C
This question includes an explanation.
Explanation:
When a change request is received, the business analyst is responsible for analyzing the impact on business and underlying systems. The business analyst should assess how the change request will affect the business needs, objectives, and value, as well as the existing or planned systems, processes, and functions. The business analyst should also evaluate the feasibility, priority, and urgency of the change request, and provide recommendations and alternatives to the stakeholders. References: PMI Professional in Business Analysis (PMI-PBA)® Examination Content Outline1, page 23; Business Analysis for Practitioners: A Practice Guide2, page 132.
PMI-PBA PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 60% Discount on All Products,
Use Coupon: "8w52ceb345"