The document that defines the process for managing requirements revisions is the:
A.
project management plan.
B.
change management plan.
C.
communications management plan.
D.
scope management plan.
The Answer Is:
B
This question includes an explanation.
Explanation:
The change management plan outlines the process for managing changes to requirements, ensuring that any revisions are controlled and documented throughout the project lifecycle. References: PMI-PBA® Examination Content Outline, Business Analysis for Practitioners: A Practice Guide.