Which statement accurately depicts what changes can be made to requirements after they are baselined?

Which statement accurately depicts what changes can be made to requirements after they are baselined?

A.

Requirements can be changed only with sponsor approval.

B.

Requirements can be changed through a defined process.

C.

Requirements cannot be changed once development begins.

D.

Requirements cannot be changed once user acceptance testing begins.