A sponsor requests a new requirement.

A sponsor requests a new requirement. The business analyst explains that most of the information needed for this requirement does not exist and that the requirement cannot be implemented. The business analyst recommends deferring the requirement until the needed information is available and then adding it to a subsequent project. The sponsor agrees.

What should the business analyst do next?

A.

Bring the subsequent project to the change control board (CCB).

B.

Ask the stakeholders to review the requirement before any other action is taken.

C.

Communicate that the status of this requirement has changed.

D.

Mark the requirement as complete so that it is not forgotten.

PMI-PBA PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-PBA pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"