A team is running a forecasting project and wants to use previous user data to...

A team is running a forecasting project and wants to use previous user data to better predict future outcomes. However, the team does not have access to all the data they need.

Which action should the project manager take?

A.

Move forward in order to remain on schedule with the project

B.

Move forward while anticipating data access is given when needed. An iterative approach provides the ability to return to steps as needed later on

C.

Do not move forward until access is given to all the necessary data

D.

Move forward cautiously with the understanding that there may be a need for a pause mid-project

PMI-CPMAI PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-CPMAI pdf
Get 75% Discount on All Products, Use Coupon: "ac75sure"