PMI PMI-ACP Question Answer
While reviewing the sprint burndown during a stand-up, the Scrum team identifies that they have fallen behind. Upon further discussion, they discover that some quality assurance (QA) team members were unable to use the new automation framework, which caused a bottleneck.
What should the Scrum team do?