What should the product owner have done differently?
A.
Demonstrated only the completed stories and seek stakeholder feedback
B.
Presented the budget situation and review the cost variance
C.
Reviewed the test results to gain confidence from the stakeholders
D.
Presented a demo of all the stories including the work in progress stories
The Answer Is:
A
This question includes an explanation.
Explanation:
Iteration reviews (or sprint reviews) are designed to demonstrate completed, potentially shippable product increments. According to the PMI Agile Practice Guide (Section 5.3 Sprint Review and Acceptance), the purpose of the iteration review is to showcase work that meets the Definition of Done (DoD) and to receive stakeholder feedback. Demonstrating incomplete or in-progress stories can mislead stakeholders about progress and reduce trust in the team.
Mike Griffiths in the PMI-ACP Exam Prep Book (Chapter 6: Value-Driven Delivery) emphasizes the importance of showing only completed work to maintain transparency and clarity in stakeholder communication.
Option A is correct: only completed stories should be demoed to ensure expectations are managed effectively.
Option B and C are not part of the typical iteration review agenda unless explicitly required.
Option D is incorrect, as it blurs the line between done and in-progress work.
PMI-ACP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"