Determine the required tasks for implementing the high-level features
B.
Identify the detailed design for the high-level features
C.
Prioritize the product backlog for the upcoming release
D.
Estimate the user stories in the iteration backlog
The Answer Is:
C
This question includes an explanation.
Explanation:
After the product vision is communicated, the product owner should ensure that the product backlog is prioritized so the team can focus on delivering the most valuable features first. According to the PMI Agile Practice Guide (Section 5.1 Product Backlog and Vision Alignment), prioritizing the backlog helps teams understand the product roadmap and plan their efforts accordingly.
Mike Griffiths in the PMI-ACP Exam Prep Book (Chapter 6: Adaptive Planning) reinforces that the product owner’s key responsibility is backlog prioritization, not task management or detailed design.
Option C is correct: prioritizing the backlog enables the team to understand and plan the roadmap.
Option A and B are too detailed for the product owner and move into the team ' s domain.
Option D is a team responsibility, not the product owner’s.
PMI-ACP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"