Require the team to try only those ideas that will ensure success.
B.
Allow the team to try ideas, but remind them that results will be reviewed by high-ranking executives.
C.
Associate idea successes and failures with the team ' s incentive plan to ensure accountability.
D.
Encourage the team to try the ideas, even if failure may be the outcome.
The Answer Is:
D
This question includes an explanation.
Explanation:
Agile fosters a safe-to-fail environment where experimentation is encouraged. According to the PMI Agile Practice Guide (Section 5.6: Retrospectives and Process Improvement) and Mike Griffiths’ PMI-ACP Exam Prep Book (Chapter 7: Continuous Improvement), teams should be empowered to test new ideas and learn from outcomes, regardless of whether those experiments succeed or fail.
Option D is correct: promoting experimentation supports learning and innovation.
Option A discourages risk-taking and limits growth.
Option B creates fear and undermines psychological safety.
Option C mixes accountability with experimentation, which can discourage honest learning.
PMI-ACP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"