Adhere to the new deadline and immediately advise the client that the schedule has been expedited.
B.
Advise the client that it is best to continue as planned rather than introduce unforeseen risks by expediting the schedule.
C.
Submit a change request to the client with a 50% increase in charges due to the new potential profit.
D.
Request additional resources to meet the expedited deadline and obtain training for the new resources.
The Answer Is:
A
This question includes an explanation.
Explanation:
Agile teams embrace change and collaborate with customers to deliver value. The PMI Agile Practice Guide (Section 2.1: Agile Mindset) supports responding to change—even late in the development cycle—if it results in business value. The team should accept the new goal, replan with the product owner, and adjust scope or priority if needed, rather than resist or escalate.
Option A is correct: it reflects the agile value of responding to change and delivering early value.
Option B is too rigid and contrary to agile principles.
Option C implies a punitive model that does not align with collaborative agile contracts.
Option D introduces unnecessary cost and overhead without first trying to replan collaboratively.
PMI-ACP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"