Identify a team member to do a proof of concept using this framework.
B.
Email the team directing them to immediately begin using this new framework.
C.
Obtain feedback from team members on the new framework, and then suggest that the product owner create a backlog item to do a spike on it.
D.
Discuss this option at the next retrospective.
The Answer Is:
C
This question includes an explanation.
Explanation:
Agile teams evaluate new tools or technologies through spikes—time-boxed research or experimentation tasks. According to the PMI Agile Practice Guide (Section 5.2: Spikes and Exploration) and Mike Griffiths’ PMI-ACP Exam Prep Book (Chapter 6: Adaptive Planning), the appropriate way to introduce new technology is to engage the team in the decision and create a backlog item for a spike to evaluate its viability.
Option C is correct: it follows agile collaboration and backlog grooming practices.
Option A skips team consensus and formal prioritization.
Option B contradicts self-organizing team principles.
Option D may delay necessary action and is better suited for process discussions, not technical trials.
PMI-ACP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"