Ask the product owner to inform all stakeholders about the project ' s progress.
B.
Send meeting notes to all stakeholders after each review meeting.
C.
Include the results of the review meetings in the information radiators.
D.
Convince the stakeholders of the benefits of attending the review meetings.
The Answer Is:
D
This question includes an explanation.
Explanation:
Stakeholder participation, especially during sprint reviews, is critical to agile success. The PMI Agile Practice Guide (Section 7.2: Stakeholder Engagement) emphasizes the importance of actively engaging stakeholders throughout the project lifecycle, particularly during key ceremonies like sprint reviews, where feedback shapes the product.
Mike Griffiths in the PMI-ACP Exam Prep Book (Chapter 4: Stakeholder Engagement) states that stakeholders need to understand the value of their input and how it influences product direction. The agile practitioner or Scrum Master should educate and influence stakeholders by demonstrating the tangible impact of their participation.
Option D is correct: aligning stakeholders with the benefits of engagement fosters participation.
Option A, B, and C are passive substitutes and don’t address the root issue of stakeholder disengagement.
PMI-ACP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"