Work with the team to determine points at which to celebrate its work.
B.
Provide the team with a break by scheduling a team event.
C.
Have the team increase work in progress (WIP) levels to more quickly complete the flow.
D.
Rejuvenate the team by temporarily reducing WIP levels.
The Answer Is:
A
This question includes an explanation.
Explanation:
Kanban is continuous and can lead to burnout or low morale due to lack of visible milestones. The PMI Agile Practice Guide (Section 5.7: Flow-based Agile) and Mike Griffiths’ PMI-ACP Exam Prep Book (Chapter 3: Team Performance) suggest that recognizing and celebrating milestones or delivery points is essential to maintain motivation, especially in long-running Kanban teams.
Option A is correct: celebrating completed work gives the team a sense of closure and achievement, improving engagement.
Option B might help temporarily but doesn’t address the root motivational issue.
Option C adds pressure and is counterproductive.
Option D may improve flow but doesn ' t directly address the lack of visible progress recognition.
PMI-ACP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"