Have other team developers attend training to learn database skills.
B.
Monitor the retrospectives of two additional sprints before taking action.
C.
Plan fewer stories for the sprint to reduce the database engineers ' workload.
D.
Ask the Scrum Master to work with the product owner to remove backlog stories that have database dependency.
The Answer Is:
A
This question includes an explanation.
Explanation:
Agile promotes cross-functional teams and reducing bottlenecks through knowledge sharing and skill development. The PMI Agile Practice Guide (Section 4.3.3: Cross-functional Teams) recommends that team members develop T-shaped skills to handle more types of work. Mike Griffiths in the PMI-ACP Exam Prep Book (Chapter 3: Team Performance) advocates for skill broadening to improve team throughput and resilience.
Option A is correct: cross-training removes dependencies and improves flow.
Option B delays action and prolongs the issue.
Option C reduces delivery capacity rather than addressing the root cause.
Option D arbitrarily limits scope and doesn’t resolve the underlying skill gap.
PMI-ACP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"