Summer Special Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 8w52ceb345

Unable to meet a sprint's committed velocity, an agile team approaches the agile coach to...

Unable to meet a sprint's committed velocity, an agile team approaches the agile coach to define the next sprint's velocity. What should the agile coach advise?

A.

Split each story into multiple stories to meet the desired velocity.

B.

Set the velocity to the delivered story points of the last sprint.

C.

Use different estimation methods for stories and defects to meet the desired velocity.

D.

Re-estimate by assigning more story points to smaller stories to increase the velocity.

PMI-ACP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-ACP pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"