The systems integrator for an enterprise resource planning (ERP) project has been onboarded.

The systems integrator for an enterprise resource planning (ERP) project has been onboarded. During an iteration planning session, the team determines that the next highest priority item will take longer than expected to complete in the current sprint.

What should the agile practitioner do next?

A.

Schedule a meeting with the product owner to review the sprint priorities.

B.

Put the high-priority item back into the product backlog.

C.

Extend the sprint end date to accommodate the high-priority item.

D.

Ask the project sponsor to add more resources to ensure timely completion.

PMI-ACP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-ACP pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"