Summer Special Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 8w52ceb345

The risk profile of a project has increased beyond the upper threshold of tolerance.

The risk profile of a project has increased beyond the upper threshold of tolerance. The product owner and project leader meet to discuss an approach for dealing with this. What should the team do next?

A.

Add risk mitigation tasks to the backlog, then prioritize in current and upcoming sprints

B.

Add risk mitigation time to each requirement

C.

Apply the 80/20 rule, reserving 20 percent of each sprint’s capacity for risk mitigation

D.

Hold all risks until they become issues, then add issue resolution tasks to the product backlog

PMI-ACP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-ACP pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"