The manager of the team is responsible for delivering a specific initiative within the organization.

The manager of the team is responsible for delivering a specific initiative within the organization. They are preparing for the monthly project review meeting, where they will present the current state of this initiative. The agile project lead sends the manager the following email with the initiative's current status.

Which summaries are correct and will be presented during the monthly project review? (Refer to

the email and exhibits to the Team Manager)

A.

MVP has 25 remaining story points; MVP will complete at the end of sprint 8; with no otherdeviations, the entire backlog will complete at the end of sprint 15.

B.

MVP has 30 remaining story points; MVP will complete at the end of sprint 8; with no otherdeviations, the entire backlog will complete at the end of sprint 15.

C.

MVP has 25 remaining story points; MVP will complete at the end of sprint 9; with no otherdeviations, the entire backlog will complete at the end of sprint 16.

D.

MVP has 30 remaining story points; MVP will complete at the end of sprint 9; with no otherdeviations, the entire backlog will complete at the end of sprint 16.

PMI-ACP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-ACP pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"