The correct answer is A – The Agile team should engage stakeholders regarding the proposed designs and ensure that sufficient engagement occurs throughout the project in an adaptive way.
Agile thrives on continuous stakeholder engagement. Ignoring feedback or rigidly sticking to past decisions defeats Agile's principle of responding to change over following a plan. Even if designs have been created, collaboration must continue.
From the PMI Agile Practice Guide:
“Engaging stakeholders early and often helps ensure alignment and mitigates late surprises. Adaptive planning allows for feedback and refinement throughout the lifecycle.”
(PMI Agile Practice Guide, Section 4.2 – Stakeholder Engagement)
Mike Griffiths emphasizes:
“Stakeholder collaboration and frequent inspection are cornerstones of Agile. Late feedback is better than no feedback. Teams must adapt.”
(Mike Griffiths, PMI-ACP Exam Prep Book, Chapter 3 – Stakeholder Engagement)
Other options:
B discourages collaboration.
C emphasizes documentation over interaction.
D is drastic and unnecessary.
Answer: A
══════════════════════════════════════════════════