Use agile estimation techniques to create a shared understanding of when the user stories will be completed.
B.
Agree upon development and testing activities for the user stories.
C.
Complete the user stories, and provide a demo for the product owner and customer.
D.
Complete the user stories, and hold a retrospective to discuss them.
The Answer Is:
A
This question includes an explanation.
Explanation:
Once the team has clarity on the user stories and agrees they are ready, the next step in agile planning is toestimatethem. According to thePMI Agile Practice Guide (Section 5.2: Estimating)andMike Griffiths’ PMI-ACP Exam Prep Book (Chapter 6: Adaptive Planning), agile estimation techniques likestory pointsorPlanning Pokerhelp the teamgain a shared understanding of effort, complexity, and delivery time.
Option Ais correct: estimating comes before development and guides prioritization and planning.
Option Bprematurely dives into task-level detail before effort is understood.
Option Cskips planning and development entirely.
Option Drefers to retrospective, which comes after execution, not before.
PMI-ACP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 60% Discount on All Products,
Use Coupon: "8w52ceb345"