What should the Scrum Master mention at the next retrospective?
A.
Solutions to project problems that were built into the last sprint
B.
Problems that arose
C.
Solutions that saved the organization the most time and money
D.
Problems that were solved
The Answer Is:
B
This question includes an explanation.
Explanation:
Retrospectives are held toinspect what went well and what could be improved. According to thePMI Agile Practice Guide (Section 5.6), teams should use retrospectives to identifyissues, root causes, and impediments, not just successes. Identifying and discussing theproblems that arosehelps the team avoid similar issues in future sprints.
Mike Griffiths in hisPMI-ACP Exam Prep Book (Chapter 7: Continuous Improvement)emphasizes the importance of open discussions around problems and the value of asafe environmentwhere teams can reflect and improve.
Option Bis correct: by highlighting the problems that emerged, the Scrum Master sets the stage for continuous improvement and alignment with organizational goals.
PMI-ACP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 60% Discount on All Products,
Use Coupon: "8w52ceb345"