Monitor the threats and risks while allowing the team member to multitask on both projects
B.
Assign more resources to the sprints to compensate for the absences of the team member
C.
Ensure that the threats and risks are communicated and addressed
D.
Assign fewer stories to the sprints so that the team member can still meet sprint goals
The Answer Is:
C
This question includes an explanation.
Explanation:
According to thePMI Agile Practice Guide (Section 7.2.1), the Scrum Master’s role includesremoving impediments and shielding the team from outside interference. A team member being pulled into work on a different project is a classic example of an impediment. Recording the issue in a risk register is appropriate, but more importantly,the Scrum Master must communicate and resolve the issue.
Mike Griffiths in hisPMI-ACP Exam Prep Book (Chapter 3: Team Performance)emphasizes that agile teams require full dedication and protection from context switching, as multitasking reduces productivity and increases error rates. Merely documenting the issue is not enough—the Scrum Master must take steps toescalate and resolve the interference, potentially by negotiating with the former supervisor or re-clarifying role boundaries.
Therefore,Option Cis correct as it involvesactively addressing the threatrather than passively monitoring or adjusting around it.
PMI-ACP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 60% Discount on All Products,
Use Coupon: "8w52ceb345"