Assign the spike to another resource to continue research for the long-term solution
B.
Re-establish the spike; encourage experimentation and collaborate with the team
C.
Stop experimentation and negotiate the short-term solution with the customer
D.
Schedule a root-cause analysis with the development team on the main issues with the spike
The Answer Is:
B
This question includes an explanation.
Explanation:
Spikes are meant forexperimentation and learning, not guaranteed outcomes. According to thePMI Agile Practice Guide (Section 5.2 Spikes), if a spike does not lead to a clear solution, the team can extend or reframe it, especially when aiming for asustainable long-term solution. Agile supportsencouraging experimentationand learning from failure.
Mike Griffiths (PMI-ACP Exam Prep Book, Chapter 7: Problem Detection and Resolution) recommends adapting when a spike’s results are inconclusive—redefining the scope and collaborating as a teamincreases the chance of a valuable outcome.
Option Bis correct: it continues learning and promotes team collaboration.
Option Aundercuts team ownership.
Option Cprioritizes a short-term fix and undermines agile values.
Option Dis not needed at this early stage—root cause analysis is better for recurring or systemic issues.
PMI-ACP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 60% Discount on All Products,
Use Coupon: "8w52ceb345"