Work with the team to determine points at which to celebrate its work.
B.
Provide the team with a break by scheduling a team event.
C.
Have the team increase work in progress (WIP) levels to more quickly complete the flow.
D.
Rejuvenate the team by temporarily reducing WIP levels.
The Answer Is:
A
This question includes an explanation.
Explanation:
Kanban is continuous and can lead toburnout or low moraledue to lack of visible milestones. ThePMI Agile Practice Guide (Section 5.7: Flow-based Agile)andMike Griffiths’ PMI-ACP Exam Prep Book (Chapter 3: Team Performance)suggest thatrecognizing and celebrating milestones or delivery pointsis essential to maintain motivation, especially in long-running Kanban teams.
Option Ais correct:celebrating completed workgives the team a sense of closure and achievement, improving engagement.
Option Bmight help temporarily but doesn’t address theroot motivational issue.
Option Cadds pressure and is counterproductive.
Option Dmay improve flow but doesn't directly address thelack of visible progress recognition.
PMI-ACP PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 60% Discount on All Products,
Use Coupon: "8w52ceb345"