How can the scrum master respond to a stakeholder who suggests using velocity as a...

How can the scrum master respond to a stakeholder who suggests using velocity as a metric to measure team efficiency in an agile project?

A.

Velocity of a Scrum team will stop once it becomes stable and only then the team will become efficient with its deliverables.

B.

Velocity can only measure if a Scrum team has a stable and predictable run rate but not whether or not they are delivering better deliverables efficiently.

C.

Velocity will become more predictable only in stable teams and velocity should not be measured in Scrum teams until that occurs.

D.

Velocity is a great way of measuring the Scrum team's efficiency, and a stable velocity means the team is predictable and efficient.

PMI-ACP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-ACP pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"