During a six-week iteration, an issue is identified by a team member.

During a six-week iteration, an issue is identified by a team member. After analysis, the team member determines that it will take at least two weeks to resolve. What should the team member do?

A.

Notify the product owner and begin resolution.

B.

Communicate the issue to the team in the next stand-up meeting.

C.

Immediately begin resolution, and communicate it to the team during the retrospective.

D.

Work on the next activity, and communicate it to the team during the retrospective.