The correct answer is A – The team will be unable to understand the iteration's status. Agile relies on transparency and timely updates to progress tracking tools such as task boards, burndown charts, and digital boards. Incomplete or delayed updates obscure the team's true progress, making it difficult to inspect and adapt.
From the PMI Agile Practice Guide:
“Visibility of progress is key to agile. Without timely updates to task boards or status indicators, teams lose the ability to inspect and adapt effectively during iterations.”
(PMI Agile Practice Guide, Section 5.2 – Information Radiators)
Mike Griffiths emphasizes:
“If user stories or tasks are not updated, burndown charts and velocity metrics become inaccurate. This compromises team transparency and decision-making.”
(Mike Griffiths, PMI-ACP Exam Prep, Chapter 6 – Problem Detection and Resolution)
Incorrect options:
B is not directly impacted by status updates.
C might result as a side effect, but A is more fundamental.
D misrepresents the problem—it is about progress tracking, not collaboration metrics.
Answer: A
────────────────────────────────────