A Scrum team is refining product backlog items for the next sprint in a project.

A Scrum team is refining product backlog items for the next sprint in a project. The product owner does not agree with the changes.

Can the product owner reject changes to a product backlog?

A.

Yes, the product owner is part of a Scrum team and can reject any changes on the product backlog.

B.

Yes, because the product owner is the decision maker for product backlog changes.

C.

No. because this action will create disruption in the Scrum team.

D.

No. because only members of the Scrum team can reject or approve changes.