A new stakeholder has recently joined a project.

A new stakeholder has recently joined a project. During a meeting with the Scrum Master, the new stakeholder tries to understand the status of the project and the remaining tasks for completion.

How should the Scrum Master inform the new stakeholder?

A.

Show the stakeholder the latest release breakdown for the project.

B.

Invite the stakeholder to attend the next sprint review meeting.

C.

Show the stakeholder the progress radiators for the project.

D.

Invite the stakeholder to attend the next sprint planning meeting.