A mobile application project is halfway through development.

A mobile application project is halfway through development. The team reaches a stabilized velocity after 8 iterations. The sprint duration is two weeks and requirements assigned by the product owner are not changing frequently.

What is the estimated time remaining for the project?

A.

Eight months

B.

Two months

C.

Four months

D.

Six months