While reviewing the sprint burn down during a stand up.

While reviewing the sprint burn down during a stand up. The scrum team identifies that they have fallen behind Upon further discussion they discover that some quality assurance (QA) team members were unable to use the new automation framework, which caused a bottleneck.

What should the scrum team do?

A.

For upcoming sprints, have QA team members ensure that their respective skill sets are considered when acceptingstones

B.

Have QA team members with the appropriate skill sets spend extra time to help the team succeed

C.

Ensure that QA team members who lack the appropriate skill sets sign up for training within the next few weeks

D.

Ask QA team members experienced with the new automation framework to cross-train the other QA members

PMI-200 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-200 pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"