In a project, the customer asks for a requirement that clearly deviates from the contract...

In a project, the customer asks for a requirement that clearly deviates from the contract terms. How should the contractor react?

A.

Proceed with the work only after the contract is amended.

B.

Discuss the value of the change for the project with the customer.

C.

Evaluate effort and impact and ask for steering committee and shareholder approval.

D.

Stick with the contract terms and agree to review the requirement if time allows.