An agile team is in their 2nd iteration planning session.

An agile team is in their 2nd iteration planning session. During the session, they are debating on whether regression and integration testing should be part of every iteration or part of the hardening iteration.

What should the agile lead recommend?

A.

Integration testing with other upstream or downstream applications and all bug fixes should be done as part of the hardening iteration.

B.

Integration testing with other upstream or downstream applications should be done by the team as part of every iteration.

C.

Continuous integration and regression testing should be done by the team as part of every iteration.

D.

Regression testing should not be done by the team as part of every iteration but only as part of the hardening iteration.

PMI-200 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-200 pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"