A team is building a product in three-week iterations.

A team is building a product in three-week iterations. During the last retrospective, it was identified that there was a 20 percent increase from previous iterations in the number of reported defects and change requests.

Since this is causing the product's value to decrease, what should the team do?

A.

Reevaluate the duration of the cycles, as faster cycles may allow for earlier detection of defects.

B.

Run a sprint to clear all reported defects before taking new stories.

C.

Change the control mechanism so that items are better tested before delivery.

D.

Increase the opportunities to confirm common understanding with the client.

PMI-200 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-200 pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"