A Scrum team is visualizing the blockers that arise when they work on their activities...

A Scrum team is visualizing the blockers that arise when they work on their activities on the kanban board. The team decided to analyze why the blockers occur so they can take action to minimize their occurrence and reduce lead times.

Which practices should the team use?

A.

The most important principle in Scrum is reducing work in process (WIP). The lower the number of items, the lower the risk of items getting blocked. Based on the team’s capacity, they should set the lowest WIP limits possible.

B.

The team should look at all the blockers, determine the reason behind them, group them, and determine if there is a pattern. They should then determine what and how they can make relevant changes.

C.

The team should discuss the issue with their scrum master because it is their responsibility to remove impediments, such as blockers, in cooperation with other teams.

D.

Blockers are a result of bottlenecks. The team should ask for more resources to prevent bottlenecks from arising and reduce the risk of long lead times.

PMI-200 PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMI-200 pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"